Implementation
In 2011, we implemented an IAM project for an international insurance company in nine months using Scrum, which had previously failed several times over three years. This was the company's first experience with an agile project approach.
Based on this positive experience, the company gave us the go-ahead to implement a digitalisation and print project (worth 21 million) with distributed teams and components using Scrum. We also overcame this hurdle and provided the Group with a complete new digitalisation and print solution within 18 months. Since 2016, the insurance company has been using Scrum or the SAFe framework as the project methodology for 70% of its projects.
Since 2011, we have further refined our roadmap for agile transformation and also applied it very successfully in the finance and software industry. If you would like to find out more about the project and the client, please do not hesitate to contact us.